A general contractor building a new commercial plaza needed the site cleared and grubbed ahead of their excavation subcontractor, on a fixed two-week window tied to the overall project schedule.
The site had scattered mature trees and dense brush along its perimeter, plus a stand of trees near the building pad that needed to come down before excavation equipment could safely operate. The GC's schedule left no room for delay.
Work was coordinated daily with the GC's site superintendent to keep clearing crews and equipment separated from other active trades on site. All work followed the GC's site-specific safety orientation and PPE requirements.
The site was cleared and grubbed within the two-week window, and the excavation subcontractor mobilized on schedule with no delay to the overall project timeline.